TxDOT I-30 EXPANSION PROJECT UPDATES
(Click the image below to go to their website.)
PROJECT DETAILS/OVERVIEW
The I-30 expansion project will widen I-30 from Bass Pro Dr. to the Hunt County Line and add continuous frontage roads, including across Lake Ray Hubbard. The current configuration is inadequate to handle traffic congestion and population growth, and results in bottlenecks and road closures when there is an incident on the lake bridge. Adding separate frontage road bridges and expanding the mainlanes means traffic can continue to cross the lake if an incident has closed or limited general purpose lanes.
Work: Will construct from 0 to 6 lane frontage roads, Bayside Dr. bridge & ramp modifications, as well as reconstruct the Dalrock Rd. interchange
Est. Completion: Aug. 2024
Contractor: Sema Construction, Inc.
Fall 2022 Segment 1 Updates:
Continue construction of the eastbound frontage road.
Begin pouring the bridge deck for the eastbound mainlane widening bridge.
The Dalrock Flyover substructure is nearing completion.
Mobilizing cranes and drilling units to the westbound frontage road to begin drill shafts in the water.
Building retaining and sound walls
Reconstruction of Bayside Drive
Continue work on Dalrock underpass
Segment 2 (Letting in Fall 2022):
Limits: Dalrock Rd. to SH 205
CSJs: 0009-12-215 & 0009-12-220*
(Dalrock Rd. to east of Horizon Dr.)
Est. Construction: To begin late 2022
Est. Cost: $89 million (CSJ 009-12-215), $172 million* (CSJ 009-12-220)
Work: Add shoulder, reconstruct, and widen existing 6 mainlanes to 8, construct 0 to 6 lane frontage roads over the lake, reconstruct existing frontage roads, ramp modifications
Segment 3 (Letting in Fall 2022):
Limits: SH 205 to Hunt Co. Line
CSJ: 0009-12-219
Est. Construction: To begin late 2022
Est. Cost: $289 million
Work: Reconstruct and widen 4 mainlanes to 6, reconstruct and widen 4 frontage roads to 4/6, construct new & reconstruct existing interchanges, ramp modifications